S curve

Also known as: S-curve, cumulative cost curve, cash flow curve, progress curve

Definition

An S curve is a graph of cumulative cost, value or progress plotted over a project's duration. It gets its name from its shape: slow at the start during establishment, steep through the main construction phase and flattening towards completion. Builders use it to compare planned against actual progress and cash flow.

How an S Curve Works

An S curve plots time along the horizontal axis and a cumulative measure on the vertical axis. That measure might be cost, earned value, labour hours or percentage complete.

The shape follows the natural rhythm of a construction project. Early months are slow: site establishment, demolition, piling and footings. Spending then accelerates as structure, services and fit-out run in parallel with many trades on site. Towards the end, the remaining work is finishes, commissioning and defects, so the curve flattens out.

The planned S curve is usually built by loading the cost plan or contract sum onto the construction programme, so each activity's value is spread over its planned duration and added up month by month.

What an S Curve Shows

The value of an S curve comes from comparing lines on the same chart:

  • Planned or baseline curve. Expected cumulative value or cost if the project runs to programme.

  • Actual cost curve. What has really been spent to date.

  • Earned value or claimed curve. The value of work actually completed, often taken from progress claims.

  • Forecast curve. The expected path from today to completion.

If the earned value line falls below the planned line, the project is behind. If actual cost runs above earned value, the work is costing more than planned. Clients and financiers often ask for an S curve with each progress claim to check that claims match physical progress.

S curves are also used for cash flow. A developer or principal plots the expected cumulative payments to the contractor to plan funding drawdowns, while the contractor plots expected income against expected outgoings to subcontractors to check the project stays cash positive.

S Curve vs Gantt Chart

A Gantt chart shows individual activities as bars against time, with their start, finish and links. It answers what is happening when, and drives the critical path.

An S curve compresses the whole project into one cumulative line. It answers whether the project as a whole is on track for progress and cash flow. Builders usually need both: the Gantt chart to manage the work, and the S curve to manage the money and report to the client.

Common Mistakes With S Curves

  • Loading cost evenly across activities. Real spending is lumpy. Front-loaded items such as cranes and long lead orders distort an evenly spread curve.

  • Not rebaselining after major change. After large variations or an extension of time, a stale baseline makes every month look bad.

  • Comparing actual cost to plan only. Without earned value, you cannot tell whether overspend is because work is ahead or because it is costing more.

  • Ignoring the flat tail. Margin often erodes in the final stages, because preliminaries keep running while progress slows.

  • Using claimed value as progress. Claims can be front-loaded, so check the earned value line against what is physically built on site.

Frequently asked questions

Why is it called an S curve?

−

Because cumulative progress or cost on most projects traces an S shape: a slow start during site establishment, a steep middle when most trades are working, and a flattening at the end during finishes, commissioning and handover.

How do you create an S curve for a construction project?

−

Spread the value or cost of each programme activity across its planned duration, add up the totals for each period, then plot the cumulative amounts over time. Plot actual cost and earned value on the same chart each month to compare.

What does it mean if the actual S curve is below the planned curve?

−

If the earned value or progress line is below plan, the project is behind schedule. If it is actual cost that is below plan, it could mean the work is behind or that costs are lower, so compare it with earned value before drawing conclusions.

Who uses S curves in construction?

−

Project managers and commercial managers use them for monthly reporting, clients and quantity surveyors use them to check progress claims, and financiers use them to plan funding drawdowns on development projects.

On this page

Related terms

Browse the glossary

Finance & Budget

Track planned vs actual cost over time

Compare budget, commitments and actual cost across the life of the project and see where spending is running ahead of progress.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Finance & Budget

Track planned vs actual cost over time

Compare budget, commitments and actual cost across the life of the project and see where spending is running ahead of progress.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136