Variation

Also known as: Variation order, VO, change order (US), contract variation

Definition

A variation is a change to the work under a construction contract, such as adding, removing or altering work, or changing how or when it is done. Most Australian contracts let the principal, through the superintendent, direct variations and set out how the contract sum and time are adjusted.

How a Variation Works in Practice

A variation usually starts with a written direction from the superintendent, or a request from the contractor that the superintendent approves. Under many contracts the superintendent can first ask the contractor to price a proposed variation, so both parties can agree the cost before the work is done.

If the parties cannot agree a price, most contracts fall back to a valuation method. A common order is prices or rates in the contract first, then rates that are reasonable for the work, plus a margin for overheads and profit. A variation that delays the works can also support a claim for an extension of time.

Once valued, the variation is added to or deducted from the contract sum and claimed in the next progress claim.

Variations in AS 4000 and AS 2124

  • Every standard Australian contract has a variations clause. Check how directions must be given, who has authority to give them and how quickly you need to price them.

  • AS 4000-1997. Clause 36, Variations.

  • AS 2124-1992. Clause 40, Variations.

  • Your contract. Check special conditions that cap the value of variations, require principal approval above a threshold or bar claims made outside a time limit.

What Counts as a Variation

  • Added work. Extra scope the drawings and specification did not include.

  • Omitted work. Scope the principal removes. Many contracts limit omitting work just to give it to someone else.

  • Changed work. Different materials, finishes, levels or dimensions from those in the contract documents.

  • Changed method or sequence. A direction to do the work in a different order or way, where the contract did not already require it.

Who Can Direct a Variation

Under the standard Australian contracts, the superintendent directs variations on behalf of the principal. Directions from anyone else, such as the principal's project manager, a design consultant or a tenant, may not be valid directions under the contract unless the contract gives them that authority.

Before acting on an instruction, check who gave it and whether they have authority under the contract. If an instruction looks like a change but is not called a variation, many contracts let the contractor ask the superintendent to confirm it in writing as a variation. Do that before carrying out the work, so there is no argument later about whether it was a direction or the contractor's own choice.

Keep a variation register that records each direction, its date, who gave it, the price submitted, the amount approved and any time claimed.

Common Mistakes With Variations

  • Doing the work without a written direction. Verbal instructions on site are hard to prove later. Get the direction in writing before you start.

  • Pricing too late. Many contracts set a deadline for pricing a variation. Miss it and the superintendent may value it for you.

  • Forgetting the time impact. If the change delays the works, claim an extension of time as well as the cost.

  • Not flowing it down. Issue matching variations to affected subcontractors so your costs and theirs line up.

Frequently asked questions

Can a principal refuse to pay for a variation?

−

If the work was properly directed under the contract, the principal usually has to pay for it. Disputes tend to arise when the direction was not in writing, came from someone without authority, or the change was the contractor's own choice.

What's the difference between a variation and a latent condition?

−

A latent condition is something physical you find on site that could not reasonably have been anticipated. A variation is a change to the work. Finding a latent condition often leads to a variation for the extra work it causes.

Is a variation the same as a change order?

−

Yes, in practice. Change order is the common US term. Australian contracts such as AS 4000 and AS 2124 use variation, and the written instruction is often called a variation direction or variation order.

How are variations valued if the price isn't agreed?

−

Most contracts set a fallback order: rates or prices already in the contract where they apply, then reasonable rates for the work, usually with a margin for overheads and profit. The superintendent values it, and either party can dispute the valuation under the contract.

Can a contractor refuse a variation?

−

Generally no, if it is within the general scope of the contract. Most contracts let the contractor object only in limited cases, such as work well outside the original scope. Check the variations clause and special conditions.

On this page

Finance & Budget

Price, approve and claim every variation

Track variations from direction to approval to progress claim, with the time impact linked to each one.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Finance & Budget

Price, approve and claim every variation

Track variations from direction to approval to progress claim, with the time impact linked to each one.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136