Critical path

Also known as: Critical path method, CPM

Definition

The critical path is the longest sequence of dependent activities in a construction programme, and it sets the shortest possible time to finish the project. Any delay to an activity on the critical path delays completion unless time is recovered elsewhere. Activities off the critical path have float.

How the Critical Path Method Works

The critical path method (CPM) builds the programme as a network of activities linked by dependencies. Each activity has a duration, and each link says what must happen before something else can start, such as formwork before the slab pour, or the slab pour before the next level's columns.

The scheduling software then works forward through the network to find the earliest each activity can start and finish, and backward from the finish date to find the latest each can start and finish without delaying completion. Activities where the earliest and latest dates are the same have no spare time. Linked together, they form the critical path.

On a typical commercial building, the critical path often runs through the structure, then facade or roof to get the building watertight, then services and fit-out on the last levels, then commissioning and handover.

Critical Path and Float

Float is the amount of time an activity can slip without affecting something else.

  • Total float. How long an activity can be delayed without delaying project completion. Critical activities have zero total float.

  • Free float. How long an activity can be delayed without delaying the next activity that depends on it.

  • Negative float. The programme cannot meet a required date as it stands. Time must be recovered or an extension sought.

  • Near-critical paths. Sequences with only a little float. A small delay can make them critical, so they need watching too.

Who owns float is a common dispute. Some contracts say float belongs to the project, some to the contractor, and many say nothing. Check the programming clause and special conditions.

Why the Critical Path Matters for Delays and EOTs

Most extension of time clauses only allow extra time when a qualifying delay actually delays the date for practical completion. In practice, that usually means showing the delay hit the critical path, or used up all the float on a path so it became critical.

That is why a properly linked, regularly updated programme matters. When a delay happens, the planner inserts it into the current programme and shows its effect on the completion date. Without a credible critical path, a delay claim is hard to prove and easy for the superintendent to reject.

The critical path also changes as the job progresses. Work finishes early or late, logic changes and new scope arrives. A critical path from the baseline programme may not be the critical path six months later.

Common Mistakes With the Critical Path

  • Unlinked activities. Activities with no predecessor or successor break the network, and the software cannot calculate a true critical path.

  • Hard-coded dates. Constraints and fixed dates hide the real logic and can make the wrong activities look critical.

  • Not updating the programme. An out-of-date critical path is weak evidence in an EOT claim.

  • Ignoring near-critical work. Paths with a few days of float can overtake the critical path with one late delivery.

Frequently asked questions

What is the critical path in a construction project?

−

It is the chain of linked activities with no spare time, running from start to finish. Its total duration is the shortest time the project can be built in, so a delay to any activity on it pushes out the completion date.

What is float in a construction programme?

−

Float is spare time. Total float is how long an activity can slip without delaying completion. Free float is how long it can slip without delaying the next activity. Activities on the critical path have zero total float.

Can the critical path change during a project?

−

Yes, and it usually does. Early or late finishes, changed logic, variations and delays all shift which activities have no float. That is why the programme should be updated regularly and the critical path rechecked each time.

Why does the critical path matter for an extension of time?

−

Most contracts only grant an extension when a qualifying delay delays practical completion. A linked, up-to-date programme showing the delay on the critical path is usually the main evidence for that.

Can a project have more than one critical path?

−

Yes. Two or more paths can have equal, zero float at the same time. It means there is less room for error, because a delay on any of those paths delays completion.

On this page

Related terms

Browse the glossary

Project & Doc Management

Keep your programme live, not stuck in a PDF

Build, update and share the construction programme in one place, with baselines and progress tracked against every activity.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Project & Doc Management

Keep your programme live, not stuck in a PDF

Build, update and share the construction programme in one place, with baselines and progress tracked against every activity.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136