Cost to complete
Also known as: CTC, estimate to complete, ETC, cost to go
Definition
Cost-to-complete is the forecast of the remaining cost needed to finish a construction project, on top of what has already been spent or committed. Added to actual costs to date, it gives the forecast final cost, which commercial managers compare with budget to predict the project's margin.
How Cost-to-Complete Is Calculated
Cost-to-complete (CTC) is worked out line by line against the cost plan, not as one number at the end. For each cost code, the commercial team looks at:
Actual cost to date. Invoices paid or accrued and labour already spent.
Committed but not yet spent. The unspent balance of subcontracts and purchase orders.
Uncommitted forecast. Work that has not yet been let, priced from estimates or quotes.
Risks and known changes. Pending variations, contra charges and items the team expects to cost more.
Cost-to-complete is everything still to come. Forecast final cost equals actual cost to date plus cost-to-complete. Compare that with the budget, adjusted for approved variations on the revenue side, and you have the forecast margin.
For a deeper look, read Cost to Complete: The Number That Tells You If You Are Still Making Money.
Why the Cost-to-Complete Review Matters
Most builders run a monthly cost report, and the CTC review is its heart. It is where the project manager and commercial manager agree on what the job will really cost, rather than what the original estimate said.
A good CTC shows problems early. A trade running over budget, a subcontract package that came in higher than the allowance, or preliminaries burning faster because the programme has slipped all show up as a lower forecast margin months before the project finishes. That leaves time to act: chase variations, value engineer remaining packages or tighten site costs.
For the business, project CTCs feed into revenue recognition and cash flow forecasting, so an optimistic CTC on one job can overstate profit across the company.
The CTC review is also a good point to check the programme. If the forecast completion date has moved, time-related costs, such as supervision and crane hire, need to move with it, along with any liquidated damages exposure or extension of time claims that change the picture.
Cost-to-Complete vs Committed Cost
Committed cost is what you have signed up to pay through subcontracts and purchase orders. It is a fact on paper.
Cost-to-complete is a forecast. It includes the uncommitted balance of each package, likely variations and site costs still to be incurred. A project can be fully committed on a trade and still have cost-to-complete above zero, because the subcontractor's variations and back charges have not been settled.
Common Mistakes With Cost-to-Complete
Using budget minus spend. Remaining budget is not a forecast. If a package was let over budget, CTC must reflect the subcontract value, not the allowance.
Forgetting time-related costs. If the programme extends, preliminaries such as supervision, site sheds and cranes keep running.
Holding back bad news. Delaying a cost overrun to next month only makes the fade bigger.
Ignoring unapproved variations. Forecast the cost of directed work even before it is priced or approved on the revenue side.
No audit trail. Record why each forecast changed month to month, so movements can be explained to the business and the client.
Frequently asked questions
What does CTC mean in construction?
−
CTC stands for cost-to-complete, the forecast of how much more money is needed to finish the project. It is used in monthly cost reports to calculate the forecast final cost and the expected margin.
How do you calculate cost to complete?
−
For each cost code, add the unspent balance of committed subcontracts and purchase orders, the forecast cost of work not yet let, and allowances for known risks and changes. The total across all cost codes is the project's cost-to-complete.
What is the difference between cost to complete and estimate at completion?
−
Cost-to-complete is only the remaining cost. Estimate at completion, or forecast final cost, is the total: actual cost to date plus cost-to-complete. Commercial teams compare the forecast final cost with the budget to see the margin.
How often should cost to complete be updated?
−
Most builders update it monthly as part of the cost report, and again whenever a major package is let or a significant variation arises. On fast-moving or troubled projects some teams review high-risk cost codes fortnightly.
Related terms
Browse the glossary
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136