Site diary

Also known as: Daily site diary, daily report, site log, daily log

Definition

A site diary is the daily record kept by the site manager of what happened on a construction site: weather, labour and trades on site, plant, deliveries, work done, delays, instructions, visitors and incidents. It is one of the strongest pieces of evidence for extension of time and variation claims.

What to Record in a Site Diary

A useful site diary is filled in every working day, including days when work stops. Typical entries include:

  • Weather. Conditions through the day, rainfall and any time lost to wet weather.

  • Labour. Head count by trade and subcontractor, and hours worked.

  • Plant and equipment. What was on site, working or standing idle.

  • Deliveries. What arrived, from whom, and any problems.

  • Work completed. Areas and activities progressed, ideally referenced to the programme.

  • Delays and disruptions. What stopped or slowed work, why and for how long.

  • Instructions and visitors. Directions from the superintendent, consultants or client, and inspections by authorities.

  • Safety and quality. Incidents, near misses, hold points released and defects found.

  • Photos. Dated photos that back up the written entries.

For a deeper look, read The Site Diary: Construction’s Most Underused Legal Document.

Why the Site Diary Matters as Evidence

When there's a dispute over time or money, the side with the best contemporaneous records usually has the advantage. Contemporaneous means written at the time, not reconstructed weeks later.

For an extension of time claim, the site diary helps prove that a delay event happened, when it started and ended, and what it stopped on site. For a variation, it shows that an instruction was given, who gave it, and the labour and plant used on the extra work. For latent conditions, it records the date the condition was found and what was done next.

Diaries also matter in adjudication under the security of payment Acts, where decisions are made quickly on the documents. A clear, consistent diary is persuasive. A patchy one, with gaps on the days that matter, invites doubt.

Site Diary vs Daily Report

The terms are often used interchangeably. Where a distinction is made, the site diary is the builder's own internal record, while a daily report is a summary sent to the client, superintendent or head office.

Some contracts require the contractor to keep daily records and make them available to the superintendent. Check your contract and special conditions. Even where it isn't required, keep the diary as though it will be read by an adjudicator.

Whatever you call it, the content should be the same each day so entries can be compared over time. A consistent format also makes it easier for a relief site manager to pick up the job without losing the record.

Common Site Diary Mistakes

  • Filling it in at the end of the week. Entries written later are less reliable and less persuasive.

  • Being too vague. "Rain, some delays" is not evidence. Record times, areas, trades affected and who was told.

  • Skipping non-working days. Wet weather and lost days need recording most of all.

  • Recording opinions, not facts. Stick to what happened. Diaries can be disclosed in disputes.

  • Not linking to notices. The diary supports a claim, it doesn't replace the written notice the contract requires.

  • Editing entries later. Changing past entries undermines the whole diary. Add a dated correction instead.

Frequently asked questions

Who is responsible for the site diary?

−

Usually the site manager or site supervisor. On larger projects, foremen or site engineers may keep their own diaries for their areas, with the site manager responsible for the overall record. Subcontractors often keep their own diaries too.

Is a site diary a legal requirement?

−

There is no general law requiring one for commercial building, but many contracts require daily records, and they are essential evidence in disputes. Some licensing and home building regimes also expect records to be kept, so check your state's rules.

Can a site diary be used as evidence?

−

Yes. Site diaries are regularly relied on in extension of time claims, variation disputes, adjudication and court proceedings. They carry most weight when written on the day, signed or authenticated, and consistent with photos and correspondence.

Should a site diary be digital or on paper?

−

Either can work if it is filled in daily and kept securely. Digital diaries make it easier to timestamp entries, attach photos, search records and share them with the office, which strengthens their value as evidence.

How does a site diary support an EOT claim?

−

It shows when a delay event happened, how long it lasted and which work it affected. Combined with the programme and the formal notice of delay, it helps prove the delay was real and outside the contractor's control.

On this page

Free Playbook

The Site Management Playbook Behind Every High-Performing Site

What separates the best-run sites in Australia from everyone else, and the phased playbook to close the gap without stopping an active project.

Related terms

Browse the glossary

Site & HSEQ Management

Daily site diaries your claims can rely on

Record weather, labour, deliveries, delays and photos from site each day, timestamped and ready when you need to back up an EOT or variation.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Site & HSEQ Management

Daily site diaries your claims can rely on

Record weather, labour, deliveries, delays and photos from site each day, timestamped and ready when you need to back up an EOT or variation.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136