Security of payment
Also known as: SOP, SOPA, security of payment Act
Definition
Security of payment is the set of state and territory laws that give anyone who carries out construction work or supplies related goods and services a statutory right to progress payments, strict deadlines for responding to payment claims, and fast adjudication of disputes. Every Australian state and territory has its own Act.
How Security of Payment Works
Security of payment laws exist so that cash keeps flowing down the contracting chain. They do not replace the contract. They sit beside it and give the claimant a fast, interim way to get paid, with any final argument left for later.
The basic process is similar everywhere. The claimant serves a payment claim. The respondent has a short, fixed time to serve a payment schedule saying how much it will pay and why. If it pays less than claimed, or doesn't respond, the claimant can apply for adjudication or, in some cases, recover the amount as a debt in court. An adjudicator decides quickly, and the amount must be paid.
The Acts generally cannot be contracted out of. A clause that tries to exclude or limit the Act is usually void.
The Acts also usually give the claimant other remedies if the adjudicated or scheduled amount is not paid, such as the right to suspend work after giving notice, and in some states the right to have the principal withhold money owed further up the chain. These rights vary between states, so check before relying on them.
Security of Payment Acts by State
Each jurisdiction has its own legislation, and the details differ:
NSW. Building and Construction Industry Security of Payment Act 1999.
Victoria. Building and Construction Industry Security of Payment Act 2002, significantly amended from 15 April 2026.
Queensland. Building Industry Fairness (Security of Payment) Act 2017, known as the BIF Act.
Western Australia. Building and Construction Industry (Security of Payment) Act 2021.
South Australia. Building and Construction Industry Security of Payment Act 2009.
Tasmania. Building and Construction Industry Security of Payment Act 2009.
ACT. Building and Construction Industry (Security of Payment) Act 2009.
Northern Territory. Construction Contracts (Security of Payments) Act 2004.
Time limits, what counts as a valid claim, who can adjudicate and the rules on residential work all vary. Always check your state's Act rather than relying on what applied on your last interstate job.
Security of Payment vs Contract Payment Terms
The contract sets the agreed payment process: claim dates, assessment, certificates and payment terms. The security of payment Act sets minimum rights that apply regardless.
Where the contract is more generous, it usually applies. Where it is less generous, for example longer payment terms than the Act allows, the Act overrides it. NSW, for instance, caps payment at 15 business days for head contractors and 20 business days for subcontractors after a payment claim is made. Several Acts also deal with pay when paid clauses, which are generally of no effect.
Common Mistakes With Security of Payment
Missing the payment schedule deadline. This is the most expensive mistake a respondent can make, because it can leave them liable for the whole claim.
Giving thin reasons. In most states the respondent cannot raise new reasons in adjudication that were not in the payment schedule.
Assuming one state's rules apply everywhere. Timeframes and forms differ between states.
Ignoring the claimant's side. Claimants also lose rights by serving claims on the wrong date or applying for adjudication out of time.
Weak records. Claims and payment schedules are only as strong as the site diaries, photos and correspondence behind them. Keep them from day one, not once the dispute starts.
Frequently asked questions
Who is protected by security of payment laws?
−
Anyone who carries out construction work or supplies related goods and services under a construction contract, including head contractors, subcontractors, suppliers and consultants. Some Acts exclude or limit claims on certain residential work, so check your state's Act.
Can you contract out of the Security of Payment Act?
−
No. Every Australian security of payment Act contains a no contracting out provision. A clause that excludes, limits or changes the operation of the Act, or penalises a party for using it, is generally void.
What is the difference between a payment claim and a payment schedule?
−
A payment claim is the claimant's request for payment under the Act. A payment schedule is the respondent's written reply stating how much it will pay and, if less than claimed, the reasons why. Both must meet the Act's timing and content rules.
What happens if a payment schedule is not provided?
−
In most states, the respondent becomes liable to pay the full claimed amount on the due date. The claimant can then recover it as a debt in court or proceed to adjudication, depending on the state's process.
Is security of payment the same in every state?
−
No. The core idea is the same, but each state and territory has its own Act with different timeframes, claim requirements and adjudication rules. Victoria's Act changed substantially in April 2026.
Related terms
Browse the glossary
Free tools
All free resources
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136