Provisional sum

Also known as: PS, provisional allowance

Definition

A provisional sum is an allowance included in the contract price for work or items that cannot be accurately priced at tender, usually because the design or scope is not yet settled. When the work is done, the allowance is replaced by the actual cost, plus any agreed margin, and the contract sum is adjusted up or down.

How a Provisional Sum Works

At tender, the principal or contractor nominates an amount for an item that cannot be fully priced yet, such as rock excavation, a feature facade or service authority connection works. The amount sits in the contract sum as a placeholder.

When the work is carried out, the actual cost is compared with the allowance. If the cost is higher, the contract sum goes up by the difference. If it is lower, the contract sum goes down. Most contracts let the contractor add a margin on any increase, at a rate stated in the contract, and some deduct margin on a saving too.

The adjustment is usually processed like a variation and claimed through the normal progress claim.

For a deeper look, read Provisional Sums and Prime Cost Items: Where the Final Account Argument Starts.

Provisional Sums in AS 4000 and AS 2124

Both standard contracts have a dedicated provisional sums clause, with the margin percentage set out in the annexure.

  • AS 4000-1997. Clause 3, Provisional sums.

  • AS 2124-1992. Clause 11, Provisional sums.

  • Your contract. Check what counts as cost, whether margin applies to the whole cost or only the excess, and whether the principal must approve the supplier.

For home building work, several states have specific rules on how provisional sums must be estimated and disclosed in residential contracts. Check the domestic building legislation in your state.

Provisional Sum vs Prime Cost Item

The two are often confused. A provisional sum covers work, usually supply and installation, where the scope is uncertain. A prime cost item covers the supply of a specific item that has not yet been selected, such as tapware, appliances or floor tiles, where the installation is already priced in the contract.

Both are adjusted against the actual cost once known, and both normally attract a margin on any increase.

Setting a Realistic Provisional Sum

The allowance should be a genuine estimate of what the work is likely to cost, based on the information available at tender. Use quotes, recent rates for similar work or advice from a quantity surveyor rather than a round number.

Describe the scope the sum covers as clearly as possible, including what is excluded and whether the amount includes margin. Where the uncertainty is about quantity rather than scope, such as rock excavation, consider giving a rate as well as a sum so the final adjustment is easier to agree.

Review provisional sums during design development. Where the design firms up early, converting a provisional sum into a fixed price through a variation can reduce uncertainty for both parties.

Common Mistakes With Provisional Sums

  • Unrealistic allowances. A low provisional sum makes a tender look cheaper but leads to large adjustments and disputes later.

  • Vague descriptions. Describe exactly what the allowance covers so it is clear what falls inside it and what is a variation.

  • Too many provisional sums. Lots of large allowances mean the contract price is not really fixed. Resolve the design before tender where you can.

  • Poor cost records. Keep invoices and quotes so the actual cost can be verified when the adjustment is made.

Frequently asked questions

What is a provisional sum in construction?

−

A provisional sum is an estimated allowance in a construction contract for work that cannot be accurately priced at tender. Once the work is done, the contract sum is adjusted to reflect the actual cost, plus any margin the contract allows.

What's the difference between a provisional sum and a prime cost item?

−

A provisional sum covers work, often supply and install, where the scope is not yet defined. A prime cost item covers the supply of a specific item not yet chosen, such as tiles or appliances. Installation of a prime cost item is usually already in the price.

Is a provisional sum the same as a variation?

−

No. A provisional sum is an allowance already in the contract price for uncertain work. A variation is a change to the contracted work. The adjustment for a provisional sum is often processed the same way as a variation, which causes confusion.

Can a builder charge margin on a provisional sum?

−

Usually yes, if the contract says so. Most standard contracts let the contractor add a margin on the amount by which the actual cost exceeds the allowance, at the percentage stated in the contract. Check whether margin applies to savings too.

Why do provisional sums cause disputes?

−

Disputes usually come from allowances that were set too low, unclear descriptions of what the sum covers, or missing cost evidence. A clear scope and a realistic estimate at tender avoid most of them.

On this page

Finance & Budget

Track provisional sums against actual costs

See each allowance, the committed cost against it and the adjustment due, so nothing surprises you at final account.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Finance & Budget

Track provisional sums against actual costs

See each allowance, the committed cost against it and the adjustment due, so nothing surprises you at final account.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136