Subcontractor statement
Also known as: Subcontractor's statement, NSW subcontractor statement, statement of compliance
Definition
A subcontractor statement is a NSW form in which a subcontractor declares that, for a set period, it has paid its workers' wages, workers compensation premiums and payroll tax. Holding a valid statement protects the principal contractor from becoming liable for those unpaid amounts.
What a Subcontractor Statement Protects Against
In NSW, a principal contractor can be held responsible for some of its subcontractors' unpaid obligations. The subcontractor statement is the shield. It is made for the purposes of three laws:
Workers Compensation Act 1987 (NSW), section 175B. The principal contractor can be liable for a subcontractor's unpaid workers compensation premiums unless it holds a statement for that period.
Payroll Tax Act 2007 (NSW), Schedule 2 Part 5. The principal contractor can be liable for a subcontractor's unpaid payroll tax relating to the contract.
Industrial Relations Act 1996 (NSW), section 127. The principal contractor can be liable for unpaid wages owed to the subcontractor's employees for work under the contract.
If the principal contractor holds a statement for the period and has no reason to believe it is false, it is generally not liable for those amounts.
How a Subcontractor Statement Works
The statement covers a specific period, usually the period of the progress claim it accompanies. The subcontractor completes the form, signs it, and attaches a current workers compensation certificate of currency where required. Many head contractors require a fresh statement with every progress claim and will not pay until it is received.
The form records the subcontractor's details, the principal contractor, the contract, the period covered and declarations that workers compensation insurance was held, wages were paid and payroll tax obligations were met. The principal contractor must keep the statement for the period the legislation requires.
A subcontractor who knowingly gives a false statement commits an offence. A principal contractor who has reason to believe a statement is false loses the protection.
Head contractors usually manage this through their subcontractor compliance process, alongside insurance certificates, licences and induction records. Statements are checked when each claim comes in, and missing or incomplete statements are flagged before the payment run rather than after.
Subcontractor Statement vs Certificate of Currency
A certificate of currency is issued by an insurer and proves a workers compensation policy exists for a period. It says nothing about wages or payroll tax.
A subcontractor statement is a declaration by the subcontractor covering all three obligations. The two work together: the statement is the declaration and the certificate is evidence that the insurance part is true. Other states have different arrangements, so a NSW form is not the answer interstate.
Common Mistakes With Subcontractor Statements
Accepting a statement for the wrong period. The dates must match the claim or payment period.
Out-of-date forms. Use the current form, which cites the Payroll Tax Act 2007, not the repealed 1971 Act.
Unsigned or incomplete forms. A statement missing the signature or ABN may not give protection.
Ignoring red flags. If workers on site say they have not been paid, the principal contractor cannot simply rely on the paperwork.
Forgetting lower tiers. A subcontractor who engages its own subcontractors should also be collecting statements from them for the same period.
Frequently asked questions
Is a subcontractor statement mandatory in NSW?
−
It is not mandatory to provide one, but without it the principal contractor can be liable for the subcontractor's unpaid workers compensation premiums, payroll tax and wages. Under the Industrial Relations Act, the principal contractor can withhold payment until a statement is provided.
Who needs to sign a subcontractor statement?
−
The subcontractor, or a person authorised to sign on its behalf, such as a director. It is given to the principal contractor, usually with each progress claim, and covers the period stated on the form.
How long do you keep subcontractor statements?
−
The principal contractor must keep them for the period required by the relevant legislation. Many builders keep them for at least seven years in line with other business records. Check current Revenue NSW and SafeWork NSW guidance.
Do other states use subcontractor statements?
−
The subcontractor statement is a NSW form. Other states and territories have their own rules on principal contractor liability for workers compensation and wages, so check the local requirements on interstate projects.
Can a head contractor withhold payment without a subcontractor statement?
−
Generally yes. Section 127 of the NSW Industrial Relations Act 1996 allows a principal contractor to withhold payment until the subcontractor provides a written statement. Check that your subcontract also makes it a condition of payment.
Related terms
Browse the glossary
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136