ITP (inspection and test plan)

Site engineer measuring reinforcement spacing at an ITP hold point before a concrete pour

ITP (inspection and test plan)

Also known as: Inspection and test plan, inspection and testing plan, ITP/ITC

Definition

An ITP, or inspection and test plan, is a quality document that lists every inspection and test required for a work activity, when it happens, who does it, the acceptance criteria and the records needed. It also marks the hold points and witness points where the client or engineer must be involved.

What an ITP Is in Construction

An ITP sets out, before work starts, how a contractor will prove that an activity meets the specification. There is usually one ITP per work type, such as earthworks, formwork, reinforcement, concrete placement, structural steel, waterproofing or fire services.

The ITP is a plan. The completed record that shows each check was actually done is usually called an ITC, or inspection and test checklist, though some projects use the terms loosely. Together they form the quality evidence that the superintendent, certifier and client rely on when they accept the work.

For a deeper look, read ITP Construction - Guide for Inspection and Test Plans. Try the free ITP Builder.

What an ITP Must Include

Each line of an ITP covers one inspection or test. A typical line includes:

  • Activity. The step being checked, for example reinforcement placement before a pour.

  • Reference. The drawing, specification clause or Australian Standard that sets the requirement.

  • Acceptance criteria. What passes, such as cover to reinforcement within the stated tolerance.

  • Method and frequency. How it is checked and how often, for example one slump test per truck.

  • Responsibility. Who inspects and who signs off.

  • Inspection type. Whether it is a hold point, witness point or routine surveillance.

  • Record. The evidence kept, such as a test certificate, survey or signed checklist.

On most commercial and government projects, the specification lists the ITPs the contractor must submit and the minimum hold and witness points. The ITP is usually submitted for review before that work starts.

Hold Points vs Witness Points in an ITP

A hold point is a stop. Work must not proceed past it until the nominated person, usually the superintendent, engineer or client representative, has inspected and released it in writing. Pre-pour inspection of reinforcement is the classic hold point, because once the concrete is placed nobody can check it.

A witness point is a notification. The contractor gives notice so the nominated person can attend, but if they do not turn up within the agreed notice period, work can continue. The contractor still does the inspection and keeps the record.

Getting the notice periods right matters. Most specifications set how much notice is needed for each hold or witness point, and a missed notice can mean uncovering work at the contractor's cost.

Common Mistakes With ITPs

  • Copying a generic ITP. A template that does not reflect the project specification will miss its specific hold points and tolerances.

  • Filling in checklists after the fact. Ticking boxes at the end of the week defeats the purpose and will not stand up in a dispute.

  • Not releasing hold points in writing. A verbal "go ahead" on site leaves no record. Get the release signed or logged.

  • Forgetting subcontractors. Subcontractors should run ITPs for their own scope, and the head contractor still needs to review them.

  • No link to NCRs. A failed inspection should generate a non-conformance report, not just a note on the checklist.

Frequently asked questions

What is an ITP in construction?

−

An ITP is an inspection and test plan. It lists the inspections and tests needed for a work activity, the acceptance criteria, who is responsible, and which steps are hold or witness points, so the contractor can prove the work meets the specification.

What is the difference between an ITP and an ITC?

−

The ITP is the plan of what will be checked and how. The ITC, or inspection and test checklist, is the completed record that shows each check was done, by whom, when and with what result. Some projects combine them into one form.

What is a hold point in construction?

−

A hold point is a step in the ITP past which work must not continue until a nominated person, such as the superintendent or engineer, has inspected and released it. It is used where the work will be covered up or cannot easily be checked later.

Who prepares the ITP?

−

The contractor or subcontractor doing the work usually prepares the ITP, based on the project specification. It is then reviewed by the head contractor's quality manager and often submitted to the superintendent or client before work starts.

Is an ITP required by law in Australia?

−

Generally no single law requires one. ITPs are required by the contract and specification, and by quality management systems such as those aligned to ISO 9001. Most government and larger commercial projects make them mandatory.

On this page

Site & HSEQ Management

Run ITPs and ITCs on site, not on paper

Build ITP templates once, complete checklists on a phone, and release hold points in writing with photos and sign-offs attached.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

Site & HSEQ Management

Run ITPs and ITCs on site, not on paper

Build ITP templates once, complete checklists on a phone, and release hold points in writing with photos and sign-offs attached.

Project record

Live

Variation V-014

Priced

RFI-022

Answered

SWMS-031

Approved

Progress claim 7

Submitted

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

One platform. One data model. Every project.

Book a 30-minute walkthrough with our team, built around how you run your sites.

© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136