Dilapidation report
Also known as: Dilapidation survey, pre-construction condition report, condition survey
Definition
A dilapidation report is a dated record, with photos and written notes, of the condition of neighbouring buildings, roads and public assets before construction starts. It is used to prove whether any cracking or damage found later existed before the works or was caused by them.
How a Dilapidation Report Works
Before excavation, demolition or piling starts, an inspector visits each adjoining property and records its condition room by room and elevation by elevation. Existing cracks are photographed, measured and marked on a plan. External items such as fences, driveways, retaining walls, kerbs, footpaths and road pavement are recorded too.
Copies usually go to the builder, the owner of each inspected property and, where it is a consent condition, the council or certifier. After the works finish, or when a neighbour raises a complaint, a second inspection is done and compared against the first. Anything new or worse becomes the starting point for a damage discussion. Anything already recorded generally does not.
For a deeper look, read What is a Dilapidation Report? A Builder's Complete Guide. Try the free Dilapidation Report Builder.
When a Dilapidation Report Is Required
In Australia the requirement usually comes from the development approval, not from a single piece of legislation. Councils commonly add a condition of consent requiring dilapidation reports on adjoining properties before excavation or demolition, particularly where there is a basement, deep excavation, piling, vibration or rock breaking close to the boundary.
Other common triggers include:
Council and road assets. Many councils require a report on the footpath, kerb, gutter and road in front of the site, and may hold a bond against damage.
Utility and rail authorities. Work near sewer mains, stormwater assets or rail corridors can require condition surveys of that infrastructure.
The contract. Head contracts and subcontracts often require the builder to obtain reports even where the consent does not.
Insurance. Contract works and public liability insurers may expect them on higher risk excavation jobs.
Wording and timing differ between councils and states, so read the actual consent conditions. Some require the report to be lodged with the certifier before a construction certificate or building permit is issued.
What a Good Dilapidation Report Includes
A useful report is specific enough that someone who has never visited the site can tell what was there. It should include the property address and inspection date, the names of people present, a site plan showing where each photo was taken, clear dated photos with a scale or measurement for each crack, a written description of each defect, and notes on any areas the inspector could not access.
If a neighbour refuses access, record the refusal in writing and photograph what can be seen from the boundary or street. That record is still worth having.
Common Mistakes With Dilapidation Reports
Starting work before the report is done. Once the excavator is on site, every crack next door looks like your crack.
Photos without context. A close up of a crack with no location, scale or date is close to useless in a dispute.
Skipping the public domain. Damaged kerbs and footpaths at the end of a job are often charged against the builder unless there is a record they were already damaged.
Not sending a copy to the neighbour. Giving the owner a copy and asking them to confirm it builds trust and makes later claims easier to resolve.
Forgetting the final inspection. Without a post-construction report there is nothing to compare against.
Frequently asked questions
Who pays for a dilapidation report?
−
Usually the developer or builder carrying out the works, because the report protects them against damage claims and is often a condition of their development approval. The contract will say whether the principal or the contractor has to arrange it.
Is a dilapidation report a legal requirement in Australia?
−
Not automatically. It becomes mandatory when a council imposes it as a condition of consent, an authority requires it for work near its assets, or the contract calls for it. Even when it is optional, it is cheap protection on any job with excavation near a boundary.
Can a neighbour refuse a dilapidation inspection?
−
Yes, an owner can refuse entry. If that happens, keep the written refusal, inspect and photograph what is visible from public land or your site, and tell the certifier or council if the report is a consent condition.
When should a dilapidation report be done?
−
Before any demolition, excavation, piling or heavy vibration starts, and again once those works or the whole project are finished. Some consents set specific timing, such as lodging the report with the certifier before work begins.
Who prepares a dilapidation report?
−
Usually an independent building consultant, building inspector or structural engineer. Independence matters because the report may be relied on by both the builder and the neighbour if damage is later alleged.
Related terms
Browse the glossary
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136