Cost plus contract
Also known as: Cost plus, cost reimbursable contract, cost plus margin, do and charge
Definition
A cost plus contract is a construction contract where the principal pays the contractor's actual costs of doing the work, plus an agreed margin or fee for overheads and profit. It is used when the scope is too uncertain to fix a price, and it shifts most cost risk to the principal.
How a Cost Plus Contract Works
The contractor carries out the work and records its actual costs: labour, materials, plant, subcontractors and other agreed items. It then claims those costs, plus the agreed margin, in each progress claim, with evidence such as invoices and timesheets.
The contract defines what counts as a reimbursable cost. Anything outside that definition, such as head office costs or rework from the contractor's own defects, is usually excluded or covered by the margin. The principal, or its quantity surveyor, checks the records before paying.
For a deeper look, read The Rulebook of Revenue: A Guide to Construction Contracts.
Types of Cost Plus Arrangements
Cost plus percentage. The margin is a percentage of actual cost. Simple, but the contractor earns more as costs rise.
Cost plus fixed fee. The margin is a set dollar amount, so the contractor has no incentive to increase cost.
Cost plus with a guaranteed maximum price. Costs are reimbursed up to a cap, with costs above the cap borne by the contractor.
Target cost. Savings or overruns against an agreed target are shared between the parties in set proportions.
Cost Plus Contract vs Lump Sum Contract
Under a lump sum contract the contractor agrees a fixed price for a defined scope and carries the risk of its costs being higher than planned. Under a cost plus contract the principal pays what the work actually costs, so the principal carries that risk.
Cost plus suits early works, fit-outs with evolving design, emergency and repair work, and relationships built on trust. Lump sum suits projects with a complete design where the principal wants price certainty. For home building, some states regulate when cost plus contracts can be used, so check local domestic building legislation.
When a Cost Plus Contract Makes Sense
Cost plus is not a lesser form of contract. It is the right tool when a fixed price would mostly be guesswork. Typical situations include:
Early works. Demolition, remediation or enabling works where site conditions are unknown.
Fast-track projects. Work that has to start before the design is complete.
Refurbishment. Existing buildings where hidden conditions make the scope hard to define.
Emergency and insurance repairs. Work that needs to start immediately after damage.
The trade-off is that the principal needs more involvement, more cost reporting and a contractor it trusts. Many principals use cost plus for the uncertain stage, then switch to a lump sum once the scope is clear.
Whichever model is used, agree at the start how costs will be reported, how often forecasts are updated and who approves spending above set limits, so both parties see the final cost coming well before the end of the job.
Common Mistakes With Cost Plus Contracts
Loose definition of cost. Agree upfront what is reimbursable, including site staff, small tools, plant rates and related-party charges.
Weak record keeping. Every cost needs supporting evidence. Missing dockets and timesheets lead to rejected claims.
No budget reporting. Even without a fixed price, the principal needs regular forecasts of cost to complete.
No audit rights. Principals should have a right to audit the contractor's books for the project.
Frequently asked questions
What is a cost plus contract in construction?
−
A cost plus contract is an arrangement where the principal reimburses the contractor's actual costs of the work and pays an agreed margin or fee on top. The final price is not known until the work is done.
Are cost plus contracts allowed in Australia?
−
Yes, for commercial work they are a normal contracting option. For residential building, some states restrict cost plus contracts to certain situations or require specific disclosures, so builders should check the domestic building legislation in their state before using one.
What is a typical margin on a cost plus contract?
−
There is no standard figure. The margin depends on the project, the risk and what costs are included in the base. It is negotiated between the parties and written into the contract as a percentage or fixed fee.
What's the difference between cost plus and lump sum?
−
A lump sum contract has a fixed price for a defined scope, so the contractor carries the risk of overruns. A cost plus contract pays actual costs plus a margin, so the principal carries that risk but gets flexibility and full visibility of costs.
What is a guaranteed maximum price?
−
A guaranteed maximum price (GMP) is a cap on a cost plus contract. The contractor is reimbursed its costs plus margin up to the cap, and carries costs above it. GMP contracts often share any savings below the cap.
Related terms
Browse the glossary
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136