Working days calculator for construction contracts
Count business days between two dates, or add business days to a date, with Australian public holidays by jurisdiction, and see exactly which days were skipped.
Why construction counts days differently
Construction contracts and legislation use several different day counts, and they are not interchangeable. Calendar days include everything. Business days exclude weekends and public holidays. Working days under a particular contract may also exclude rostered days off or an inclement weather allowance.
Getting the basis wrong is not a rounding error. A notice period counted in calendar days when the contract says business days can be a week out, and a week is frequently the difference between a valid notice and a barred one.
The first question on any deadline is therefore not when, but on what basis, and the answer is in the contract or the Act, not in convention.
Public holidays are jurisdictional, and that is the trap
There is no single Australian public holiday calendar. Each state and territory declares its own, and the differences are real: Labour Day falls in different months, some jurisdictions have holidays others do not, and substitute days for holidays falling on a weekend are handled differently.
A project in one state administered by a head office in another will get this wrong unless somebody is deliberate about which calendar applies. It is usually the place where the work is performed or where the notice must be served, but the contract may say otherwise.
This calculator asks which jurisdiction and shows which specific days it excluded, so the count can be checked rather than trusted.
What this calculator does not know
It carries national holidays plus the principal state and territory holidays. It does not carry local show days, regional holidays, the AFL Grand Final Friday, or construction industry rostered days off.
Those matter. A regional show day is a public holiday in that district and will shift a deadline. Industry RDOs shift programme dates even where they do not shift legal ones.
The tool shows its working precisely so you can add what it does not know. Treat the output as a well-documented starting point rather than a final answer, particularly where a limitation period is involved.
When the answer really matters, check it twice
Most day counts are administrative and an error is recoverable. A few are not: security of payment deadlines, notice periods that operate as a condition precedent, and limitation periods.
For those, count it, have someone else count it independently, and diarise the deadline with a buffer rather than on the day. A deadline hit at 4:58pm on the last day is a deadline you got lucky on.
Our security of payment calculator handles the statutory timeframes specifically, because those Acts exclude particular days around Christmas and New Year that a general business-day count will not catch.
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136