Ask your projects data anything. Get answers in seconds. Plexa MCP Connector is live. See it in action
FREE TOOL
Extension of time calculator
Work out your EOT notice deadline and entitlement under AS 4000, AS 4902 or AS 2124, including how each form treats concurrent delay and what happens if the superintendent says nothing.
The notice period is where claims are lost
Most extension of time claims that fail do not fail on the merits of the delay. They fail because notice was given late, and the contract made timely notice a condition of entitlement.
The difficulty is that the standard forms do not agree on when the clock starts. Under AS 4000 and AS 4902 the period runs from when the contractor becomes aware of the cause and its likely effect on the programme. Under AS 2124 it runs from when the delay occurs.
That difference is not academic. A cause you become aware of before it produces any delay starts the clock at different moments under the two families, and a notice that is comfortably in time under one may be well out of time under the other.
Concurrent delay: apportioned or forfeited
Concurrent delay is where two causes operate at the same time: one entitling the contractor to an extension, one not. How the contract treats it determines whether you get anything at all.
AS 4000 and AS 4902 direct that the extension be apportioned between the causes. AS 2124 does not: where a concurrent cause is one for which the contractor is responsible, entitlement is forfeited.
This is one of the most commercially significant differences between the forms and it is frequently missed at tender, where the amendment schedule gets read for the liquidated damages rate and not for this.
Deemed grants, and the silence that helps you
Under AS 4000 and AS 4902, if the superintendent does not respond to a claim within 28 days, the extension is deemed to have been granted for the period claimed. Silence works in the contractor’s favour.
AS 2124 contains no equivalent. Silence is simply silence, and the claim remains undetermined indefinitely unless somebody pursues it.
Knowing which regime applies changes what you do when a claim goes unanswered. Under one, the correct action may be to record the deemed grant and proceed. Under the other, it is to keep pressing.
Amendments matter more than the base form
Almost no Australian contract uses a standard form unamended, and EOT clauses are among the most heavily amended. Notice periods get shortened, deemed grants get deleted, and time bars get tightened.
One common amendment replaces a 28 calendar day notice period with 20 business days. It is worth being precise about what that does: 20 business days is the same as 28 calendar days when no public holidays fall in the window, and longer when they do. The material change is not that the period is shorter. It is that the amendment usually converts the requirement into an unambiguous bar on entitlement.
Read the amendment schedule, not the standard form. The calculator lets you override the periods for exactly this reason, and the override is the normal case rather than the exception.
The AI Construction Operating System
One platform, one data model, every project. Built in Australia, for the world.
GET THE MOBILE APP
Platform
Solutions
© 2026 Plexa Pro Pty Ltd. ABN 63 668 433 136
